NPV full form and meaning
NPV is the value today of all the money a project will bring in and pay out, discounted at a chosen rate, minus what it costs now.
Official sources, checked 17 November 2026In plain English
Money received later is worth less than money today, so each year's cash flow is divided by (1 + rate) raised to the year. A positive NPV means the project earns more than the rate you used.
The rate is usually your cost of borrowing or the return you could get elsewhere.
Example
A ₹5,00,000 machine that brings in ₹1,50,000, ₹1,80,000, ₹2,00,000, ₹1,50,000 and ₹1,00,000 over five years has an NPV of ₹71,850 at 12%, so it beats a 12% return.
How it affects you
- Use NPV with the same rate to compare projects of different sizes and lengths.
Work it out
Questions people ask
What is the full form of NPV?
The full form of NPV is Net Present Value. NPV is the value today of all the money a project will bring in and pay out, discounted at a chosen rate, minus what it costs now.