GST on flat purchase: under-construction vs ready to move

A flat bought from the builder before the completion certificate carries GST: 1% of the price for an affordable home and 5% for every other home, without input tax credit, under the rates recommended by the GST Council from 1 April 2019. Once the completion certificate is issued, or the flat is first occupied, and the whole price is paid after that, the sale is outside GST. Resale flats bought from an owner carry no GST.

Official sources listed below, checked 17 November 2026
624 sq ft
Affordable housing: GST at 1%
₹42,000
Carpet area testMet (up to 60 sq m)
Value testMet (up to ₹45 lakh)
Rate1%
Price with GST₹42,42,000 (42.42 lakh)

Steps

  1. Ask the builder for the date of the completion certificate. If it has been issued and you pay the whole price after it, no GST is due.
  2. If the flat is still being built, check the two affordable housing tests: carpet area up to 60 sq m in a metro region or 90 sq m elsewhere, and value up to ₹45 lakh. Both must be met.
  3. Apply 1% if both tests are met and 5% if either fails. The builder charges it on each instalment.
  4. Check that the GST on each demand letter matches the rate and the instalment amount.
  5. Pay stamp duty separately. GST does not replace stamp duty and registration.

GST on residential property

Type of purchaseGSTInput tax credit to the builder
Affordable home under construction (both tests met)1%Not allowed
Other home under construction5%Not allowed
Ready flat, whole price paid after the completion certificate or first occupationNil (outside GST)Not applicable
Resale flat bought from an ownerNil (outside GST)Not applicable
Plot of landNil (sale of land is outside GST)Not applicable

Affordable housing tests

WhereCarpet area up toValue up to
Metropolitan regions: Bengaluru, Chennai, Delhi NCR (Delhi, Noida, Greater Noida, Ghaziabad, Gurgaon, Faridabad), Hyderabad, Kolkata and Mumbai (whole of MMR)60 sq m (645.83 sq ft)₹45 lakh
All other cities and towns90 sq m (968.75 sq ft)₹45 lakh

Worked example

A 58 sq m flat in Thane (Mumbai MMR) for ₹42,00,000, still being built, meets both tests: GST is 1%, or ₹42,000. An 80 sq m flat in Indore for ₹90,00,000 meets the area test for a non-metro city but fails the ₹45 lakh value test, so GST is 5%: ₹4,50,000. Bought ready, with every rupee paid after the completion certificate, the same Indore flat carries no GST.

Why a ready flat has no GST

Common mistakes

Questions people ask

Is GST charged on a resale flat?

No. A sale by an owner of an existing building is outside GST. Stamp duty and registration still apply.

What if my flat is 62 sq m in Pune and costs ₹40 lakh?

Pune is not in the metro list, so the limit is 90 sq m. Both tests are met, so the rate is 1%.

Can I claim the GST back?

No. GST paid on a flat bought as your home is a cost to you, and builders charging 1% or 5% do not get input tax credit either.

Is GST charged on parking, club or other charges?

Ask the builder how each charge is billed. We have not listed separate rates for these because we could not confirm them from an official source for this guide.

Official sources

  1. Ministry of Finance via PIB, recommendations of the 33rd GST Council meeting (24 February 2019), GST Council copy, checked 17 November 2026.
  2. CGST Act, 2017 (CBIC text), Schedule II paragraph 5(b) and Schedule III paragraph 5, checked 17 November 2026.

Calculators and tools

More property guides

For information only, not legal or tax advice. Rules change: check the official source or a professional before you act.