Dedicated freight corridor: Eastern and Western DFC routes

India's two dedicated freight corridors cover 2,843 route km of goods-only railway through 7 states. The Eastern corridor runs from Ludhiana (Punjab) to Sonnagar (Bihar) and the Western from Dadri (Uttar Pradesh) to JNPT (Navi Mumbai). DFCCIL says both are now complete.

DFCCIL, checked 18 November 2026
Network2,843 route km
Eastern (EDFC)1,337 km
Western (WDFC)1,504 km
Designed for480 trains a day

Source: DFCCIL, salient features (page updated 29 April 2026); milestones (page updated 30 July 2026). Checked 18 November 2026.

Eastern Dedicated Freight Corridor (EDFC)

RouteLudhiana (Punjab) to Sonnagar (Bihar)
Length1,337 km. DFCCIL's milestone page calls the 11 October 2023 trial run from New Sahnewal to New Khurja the completion of the entire 1,337 km EDFC. Its older corridor page (June 2022) gives 1,873 km including the Sonnagar to Dankuni stretch, which has since been handed to the zonal railways.
TrackDouble line electrified from Sonnagar to Khurja; single line electrified from Ludhiana (Dhandarikalan) to Khurja and Dadri.
Main trafficCoal and mineral traffic from eastern India to consumption centres in the north; designed for heavy haul.
StatesPunjab, Haryana, Uttar Pradesh and Bihar
StatusFully commissioned

Junctions with Indian Railways: Dankuni, Andal, Gomoh, Sonnagar, Ganjkhwaja, Mughalsarai, Jeonathpur, Naini/Cheoki, Prempur, Bhaupur, Tundla, Daudkhan, Khurja, Kalanaur, Rajpura, Sirhind, Dhandarikalan. Junction arrangements planned to move trains between Indian Railways and the corridor, as listed on DFCCIL's Eastern corridor page (June 2022). Dankuni, Andal and Gomoh are on the Sonnagar to Dankuni stretch.

Source: DFCCIL, eastern corridor (page updated 27 June 2022). Checked 18 November 2026.

Western Dedicated Freight Corridor (WDFC)

RouteDadri (Uttar Pradesh) to JNPT (Navi Mumbai) via Rewari, Phulera, Palanpur, Ahmedabad and Vadodara
Length1,504 km. Length as given on DFCCIL's Western corridor page (July 2022).
TrackDouble line electrified (2 x 25 kV).
Main trafficContainer traffic between the northern hinterland and the western ports, with double-stack container trains.
StatesUttar Pradesh, Haryana, Rajasthan, Gujarat and Maharashtra
StatusFully completed (trial run on the last section, JNPT to New Saphale, on 31 March 2026)

Detours around towns: the alignment runs parallel to existing lines except for detours at Diva, Surat, Ankleshwar, Bharuch, Vadodara, Anand, Ahmedabad, Palanpur, Phulera and Rewari.

Source: DFCCIL, western corridor (page updated 4 July 2022). Checked 18 November 2026.

Sections opened, corridor by corridor

Dedicated freight corridor sections opened
EasternKhurja to Bhadan194Trial run started
EasternKhurja to Bhaupur351Completed and inaugurated
EasternGanjkhwaja to Chirailpathu10031 March 2021Electric locomotive trial
EasternNew Rooma to New Sujatpur13026 February 2022Trial run, later commissioned
EasternNew DDU to New Sonnagar137Commissioned
EasternKhurja to Dadri46Commissioned
EasternChheoki to Chunar11030 September 2022Commissioned
EasternNew Kanpur to New Bhimsen2819 October 2022Commissioned, with the IR Bhimsen link line
EasternSujatpur to Karchana6231 December 2022Commissioned
EasternNew Bhimsen to New Bhaupur2528 February 2023Commissioned
EasternNew Khurja to New Khatauli13531 March 2023Single line, commissioned
EasternNew Dagmagpur to New Ahraura Road2331 March 2023Commissioned
EasternNew DDU to New Ahraura Road2731 May 2023Commissioned
EasternSahnewal (Ludhiana) to Shambhu8013 June 2023Single line, commissioned
EasternNew Pilkhani to New Shambhu9125 September 2023Single line, commissioned
EasternNew Sahnewal to New Khurja via New Khatauli11 October 2023First electric freight trial; DFCCIL marks this as completion of the 1,337 km EDFC
EasternKhurja to Sahnewal401Dedicated to the nation, with Makarpura to Gholvad and the Ahmedabad Operation Control Centre
WesternAteli to Phulera19015 August 2018First double-stack container trial
WesternRewari to Madar306Inaugurated
WesternMadar to New Palanpur35331 March 2021Trial run; dedicated to the nation on 18 June 2022
WesternNew Palanpur to New Mehsana7530 September 2022Dedicated to the nation
WesternMehsana to Sanand (North)77Commissioned
WesternDadri to Prithala5230 November 2022Electric locomotive trial
WesternRewari to Dadri12731 March 2023Operational
WesternBhestan to Sanjan10831 March 2023Commissioned
WesternNew Gothangam to New Makarpura10323 October 2023Commissioned
WesternMakarpura to Sachin130Commissioned
WesternNew Khurja to New Rewari (links the two corridors)173Dedicated to the nation
WesternNew Gholvad to New Palghar44Commissioned
WesternNew Palghar to New Saphale46Commissioned
WesternMakarpura to Sanand North138Commissioned
WesternVaitarna to Kharbao30Commissioned
WesternMakarpura to Gholvad242Dedicated to the nation
WesternJNPT to New Saphale (Vaitarna)31 March 2026Trial run; completes the WDFC

Tap a column heading to sort.

Sections as listed on DFCCIL's milestones page, grouped by corridor in roughly the order they opened. DFCCIL gives a date for some and not others; where no date is given we leave it blank.

Source: DFCCIL, milestones (page updated 30 July 2026). Checked 18 November 2026.

How a freight corridor differs from the normal railway

FeatureIndian RailwaysDedicated freight corridor
Height of rolling stock4.265 m7.1 m (Western), 5.1 m (Eastern)
Width3,200 mm3,660 mm
Train length700 m700 m or 1,500 m
Train load5,400 tonnes12,000 tonnes
Axle load22.9 tonnes25 tonnes (track), bridges and formation designed for 32.5 tonnes
Average speed25 km/hMore than 65 km/h
TractionElectric, 25 kVElectric, 2 x 25 kV
SignallingAbsolute or automatic, 1 km spacingAutomatic, 2 km spacing in automatic territory

DFCCIL also reports 564 major and 3,645 minor bridges, 225 road over bridges and 1,974 road under bridges, about 11,814 hectares of land, no level crossings, and control centres at Ahmedabad and Prayagraj. The Eastern and Western corridors were sanctioned at ₹1,24,000 crore in June 2015.

Source: DFCCIL, salient features (page updated 29 April 2026); overview (page updated 5 October 2026). Checked 18 November 2026.

Sonnagar to Dankuni

The Sonnagar to Dankuni stretch (about 538 km, Bihar, Jharkhand and West Bengal) was first part of the EDFC. In 2022 the Sonnagar to Andal section was sanctioned as a multi-tracking project and handed to East Central Railway and Eastern Railway. The 163 km Andal to Dankuni section lies in West Bengal under Eastern Railway, with junction stations at New Khana and New Dankuni, and about 97% of its land in possession.

Source: DFCCIL, Sonnagar to Dankuni (page updated 16 July 2025). Checked 18 November 2026.

Planned freight corridors

Only corridors DFCCIL lists are shown. A proposal is not a sanctioned project, and no completion dates are given for these.

CorridorStatusDetails
East-West Dedicated Freight Corridor, Dankuni to SuratAnnounced in the Union Budget 2026-27Connecting Dankuni (West Bengal) and Surat (Gujarat). DFCCIL lists the announcement on its milestones page; no length or completion date is given there.
East Coast corridor, Kharagpur to VijayawadaProposed (DFCCIL page last updated December 2022)About 1,080 km through West Bengal, Odisha and Andhra Pradesh, mostly parallel to the Kharagpur to Vijayawada coastal line.
East-West corridor, Bhusaval to Dankuni (with Rajkharswan to Andal spur)Proposed (DFCCIL page last updated December 2022)1,551 route km main line and 187 km spur (1,738 km in all) through West Bengal, Jharkhand, Odisha, Chhattisgarh and Maharashtra, later extended from Bhusaval to Palghar.
North-South corridor, Itarsi to Nagpur to VijayawadaProposed (DFCCIL page last updated December 2022)890 route km through Madhya Pradesh, Maharashtra, Telangana and Andhra Pradesh, later extended from Vijayawada to Nidubrolu.

Source: DFCCIL, milestones (page updated 30 July 2026); new corridors (page updated 23 December 2022). Checked 18 November 2026.

Questions people ask

What is the dedicated freight corridor?

A set of railway lines built only for goods trains, separate from passenger routes, so freight can run longer, heavier and faster. DFCCIL, a company under the Ministry of Railways, builds and runs them.

How long are the Eastern and Western freight corridors?

DFCCIL gives the network as 2,843 route km across 7 states. The Eastern corridor from Ludhiana to Sonnagar is 1,337 km and the Western corridor from Dadri to JNPT is 1,504 km.

Are the freight corridors complete?

The JNPT to New Saphale (Vaitarna) trial run on 31 March 2026 completed the Western corridor. DFCCIL states that both the Eastern and Western corridors are now fully completed.

Which new freight corridors are planned?

The Union Budget 2026-27 announced an East-West corridor from Dankuni to Surat. DFCCIL's older page on new corridors (December 2022) also lists proposed East Coast, East-West and North-South corridors.